Estimated Construction Start Dates Announced for 2022 Beach Nourishment Projects. The beach will remain accessible during construction. Click here for Frequently asked questions.

*All schedules are subject to change*
Estimated Equipment Staging = August – Mid September 2022
Estimated Construction Start date = Mid September
2022 with Estimated Project Duration of 35-40 days

Click here: 2022 Southern Shores Beach  Nourishment Progress Map

Public information Meeting April 4, 2022-Beach Nourishment (video): https://www.youtube.com/watch?v=cv3UYJUfOEw

ORD 2022 01 01 BEACH NOURISHMENT ORDINANCEopens PDF file   |  BN Capital Proj Ordinance Amendment #1opens PDF file

Beach Nourishment Easements

MSD Ordinance 2021 04 01 opens PDF file

Ordinance establishing two Municipal Service Districts- First Vote

MSD Public Hearing March 16, 2021-Submitted Written Comments

Public Hearing-March 16, 2021 PowerPoint Presentationopens PDF file

Public Hearing Notice -March 16, 2021 , MSD Reportopens PDF file  , Blank Easement Sample, opens PDF file

2022-Beach-Nourishment-Project-Design-and-Permitting-Expenditures-September-2020opens PDF file

DEC Association PowerPoint ToSS February 2019 Town Meeting

December 2018 Town of Southern Shores Vulnerability Assessment & Beach Management Planopens PDF file

September 2019

January 2020

May 2020

June 2020

July 2020 Project Update

September 2020 Project Update

October 2020 Project Update

November 2020 Project Update

December 2020 Project Update

January 2021 Project Update

March 2022 Project Update

April 2022 Project Update 

May 2022 Project Update